Friday Morning

Here is the state of the siding on Friday morning.  Since both short walls are mostly done (equivalent to one long side), the front is half done and the back has not yet begun, I would say the house is almost half done — at least a little more than one-third done.  The exceptions are the upper short wall on the west side, the porch ceiling, the vents that need redoing, and electrical.  Thursday night included a conversation with the project coordinator’s department since I found out that there was one.  I understand that there will be more people coming to work on the project soon.

Please note two things in the pictures below:

  • these pictures were taken more than two weeks from when the “7-10 day project” began.
  • we have had to endure the driveway and yard looking like it has for several weeks now (remember, the window project began mid-November).  It has been difficult to get into the driveway and into the house safely most of this time.

This entry was posted in Windows and Siding. Bookmark the permalink.